An update on the IN VALENTINE projects:

Paulsen Construction will continue to place sidewalks and ADA (American
Disabilities Act) sidewalk crossings. Also, expect placement of the northbound lane
from HWY 20 to 1st street mid-week. Placing 9” doweled concrete at 21’ wide for this
section of roadway may take more than one day.

IES is scheduled to continue placing conduit, wiring, and street lighting later in
the week.

Barnes Construction will continue with removals and the construction of various
project items.

The B Street Storm Sewer project (City of Valentine) has connected to the Main
Street storm sewer at B Street. Paulsen continues to replace roadway at various
locations.
Watch for restricted driving around South Hall Street and C Street new Wacky West
and Old Mill.