Points of interest on the Valentine Main Street project:
-All of the existing concrete roadway for main street has been removed. Some additional removals and sidewalk/driveway removals will follow as the new roadway is placed.
-Water Mains have been connected from the start of the project to the end of the project. Again some additional work is required.
-Expect the Sewer Main to be connected from the start of the project to the end of the project and water/sewer service connections to businesses/residences to be completed in the next few weeks. -Sidewalks are to be placed along the west side of 2nd & Main to 3rd & Main this morning and can be used tomorrow. The contractor has scheduled this work to help with “Crazy Day” celebration.
-the 2nd & Main Street intersection will be open for the week end. Next week expect periodic closures as work progresses. -Plastic is attached to the businesses along the west side of the 200 block to protect the building when placing concrete and will be removed as the concrete becomes safe to walk on.